Implementation of final agency decision.
10 C.F.R. § 708.38
in effectEffective: 2024-07-01(a) The Head of Field Element having jurisdiction over the contract under which the complainant was employed when the alleged retaliation occurred, or EC Director, will implement a final agency decision by forwarding the decision and order to the contractor, or subcontractor, involved.
(b) An employer's failure or refusal to comply with a final agency decision and order under this regulation may result in a contracting officer's decision to disallow certain costs or terminate the contract for default. In the event of a contracting officer's decision to disallow costs or terminate a contract for default, the contractor may file a claim under the disputes procedures of the contract.