How does a concessioner request arbitration of the construction cost of a capital improvement?
36 C.F.R. § 51.57
in effectEffective: 2024-07-01If a concessioner requests arbitration of the construction cost of a capital improvement determined by the Director, the request must be made in writing to the Director within 3 months of the date of the Director's determination of construction cost under § 51.56. The arbitration procedures are described in § 51.51. The decision of the arbitration panel as to the construction cost of the capital improvement will be binding on the concessioner and the Director.
Source: eCFRURL: https://www.ecfr.gov/api/versioner/v1/full/2024-07-01/title-36.xmlFetched: 7/26/2026