Waiver of procedures and time schedules
N.D. Cent. Code § 49-22-07.2
in effect49-22-07.2. Waiver of procedures and time schedules
Any utility which proposes to construct an electric energy conversion facility or an electric
transmission facility within the state may make an application to the commission for a waiver of
any of the procedures or time schedules set forth in this chapter or in the rules adopted
pursuant to this chapter. The commission, upon a finding that the proposed facility is of such
length, design, location, or purpose that it will produce minimal adverse effects, or, upon a
finding that a demonstrable emergency exists, may issue an order waiving specified procedures
and time schedules required by this chapter or by the rules adopted pursuant to this chapter,
including, but not limited to, applications, notices, and hearings, and may forthwith issue a
certificate of site compatibility, a certificate of corridor compatibility, or a route permit, with such
conditions as the commission may require.