COORDINATION OF FEDERAL AUTHORIZATIONS FOR ELECTRIC TRANSMISSION FACILITIES

10 C.F.R. Part 900
in effectEffective: 2024-07-01

10 C.F.R. § 900.1 Purpose and scope.

10 C.F.R. § 900.2 Definitions.

10 C.F.R. § 900.3 Applicability to other projects.

10 C.F.R. § 900.4 Purpose and scope of IIP Process.

10 C.F.R. § 900.5 Initiation of IIP Process.

10 C.F.R. § 900.6 Project proponent resource reports.

10 C.F.R. § 900.7 Standard and project-specific schedules.

10 C.F.R. § 900.8 IIP Process review meeting.

10 C.F.R. § 900.9 IIP Process close-out meeting.

10 C.F.R. § 900.10 Consolidated administrative docket.

10 C.F.R. § 900.11 NEPA lead agency and selection of NEPA joint lead agency.

10 C.F.R. § 900.12 Environmental review.

10 C.F.R. § 900.13 Severability.