Exception to requirement to obtain a carbon dioxide transmission pipeline certificate of authority
Ind. Code § 14-39-1-4.5
in effectSec. 4.5. A carbon dioxide transmission pipeline company is not required to obtain a carbon dioxide transmission pipeline certificate of authority under section 4 of this chapter if either of the following applies:
(1) The carbon dioxide transmission pipeline to be constructed and operated:
(A) begins and ends on the surface property above the storage facility; and
(B) does not cross:
(i) public property;
(ii) a public right-of-way; or
(iii) a parcel for which the pipeline company would be required to obtain a right-of-way or easement for the pipeline.
(2) The surface property above the storage facility crosses only one (1) or more of the following:
(A) An existing private easement.
(B) A private right-of-way.
As added by P.L.25-2025, SEC.2. Amended by P.L.213-2025, SEC.133.